We have been on enough sites to know that a solar light is only as good as its installation day. The fixture can be perfect and still fail on the first cloudy morning because the panel was pointed at a wall. So here is the field version of our LP1 manual, in the order it actually happens on site.
Walk the lot at 4pm and look at the shadows. A tree that shades the panel from 2pm to 5pm will cost you more than any wattage upgrade. If you cannot move the pole, move the panel bracket, because the panel sits separately from the head on a split design and can be aimed independently.
Then check the pole diameter: 89-105mm fits our standard bracket. Anything smaller needs an adapter, and we would rather send it before the crew is on site than after.
![]()
Set the tilt to the local latitude, minus 10 degrees if the site is dusty, because rain should be able to wash the glass. In our experience a panel at 25-35 degrees toward true south (true north below the equator) gains 15-20% over a flat mount in winter, which is exactly when the system is tightest on power.
The LED modules tilt from 15 to 45 degrees. On a parking lot, aim the outer modules so the beam edge lands inside the parking bay line, not on the neighbour's fence. Two modules aimed slightly apart give more even coverage than one module cranked to full power, and you will not need to over-size the fixture.
If the lot is served by poles on one side only, bolt a second module to the underside of the head. The controller splits output between the two, so the battery autonomy barely changes, and you cut the pole count roughly in half.
![]()
Cover the panel to force the light on, then walk the detection zone. We set the default profile to dim-standby with a full-boost on motion. Adjust sensitivity on site, because a sensor set too high will trigger on passing cars all night and flatten the pack by morning.
The fixture is integrated, so there is no separate battery box, no DC cable run and no trench. A two-person crew does 20-30 minutes per pole including the settings. Factory side, every unit has already spent 48 hours on full load and passed an IP66 spray test before it was packed, which means the faults you would normally find in week one have already been found by us. If something does go wrong, you get a serial number that traces back to a traveler card with twelve inspection records, not a shrug.
Send us photos of your site and we will mark up the pole positions and module angles for you. It takes us twenty minutes and saves the crew a day.