5. There should be no direct light source above the solar panel. To avoid misidentification and misoperation of the lighting control system.
2) Foundation
1. Installation of foundation embedded parts (demonstration diagram)
Foundation pit:
Survey the location. If the soil is hard, excavate a pit of approximately 1 cubic meter at the location where the lighting fixtures are installed (depending on the height of the lamp pole). If the soil is soft or has special requirements, the excavation depth will be determined separately.
(3) Installation
Step 1: Inspection and testing;
1. Check if the accessories are complete,
2. Test whether the lighting fixtures are working properly.
According to the demonstration mode, the lights can work normally and it can be considered that the lighting fixtures are in good condition. Test completed: Please use the remote control to set it to the desired mode.
Step 2: Assembly of lamp holder components (suitable for flying crane lamps and nighthawk lamps);
1. Remove the three screws that secure the top cover and secure it.
2. Fix the fixing bracket to the solar panel using the 6 screws of the accessory bag.
3. Adjust the angle of the solar panel in advance and assemble it with the lamp holder.
4. The connection between the solar cell module and the bracket should be firm and reliable
5. The output lines of the components should be avoided from being exposed and securely tied with ties
6. The orientation of the solar panel should face due south, based on the compass pointing
Attention; The anti slip screws need to be tightened.
Step 3: Assembly of lamp cap and lamp pole
1. Install the lamp holder that has already installed the solar panel onto the lamp pole.
Attention: The caliber on the lamp pole is 60-70MM, depending on the installation caliber of different lamps
2. Tighten the six screws of the lock lamp pole.
3. Finalize installation